.st0{fill:#FFFFFF;}

PRINCE2 Progress Reporting 

 May 3, 2023

By  Dave Litten

PRINCE2 Progress Reporting

How often progress reporting is done depends on how much control the project needs. For example:

During the design stage, for example, looser control in terms of progress reporting may be needed than during the later management stage; if the team is highly experienced, then less frequent reporting may be appropriate, whereas, for an inexperienced team, the Project Manager may wish to increase the frequency of reporting until sufficient confidence has been gained on the capability of the team.

Prince2 Controlling A Stage

Progress reporting products

Within PRINCE2, the following are the management products that are used for progress reporting:

Checkpoint Report.

The Team Manager will produce this to provide the Project Manager with details of progress reporting against the Work Package, including the frequency of Checkpoint Reports required.

The Project Manager will consolidate Checkpoint Reports and use these as part of the progress reporting and assessment when reviewing stage status and leading to the creation of Highlight Reports.

Highlight Report.

The Project Manager produces this progress reporting document on how the management of the stage and its progress is going for the Project Board.

The Project Board will determine the frequency of Highlight Reports required for their progress reporting requirements, either for the whole project or stage by stage and document how progress reporting will occur in the Communication Management Approach.

The Highlight Report allows members of the Project Board to manage by exception between end-stage assessments by providing progress reporting to them. The report also includes information on project issues, as they know when to consider or reject the recommendations in the Issue Report.

If an Exception Plan is requested, the Project Board will conduct an exception assessment, similar to the end-stage assessment, to review and approve the Exception Plan.

The Project Board may also remove the cause, accept and adjust tolerance, or request more time to consider or reject the recommendations in the Issue Report.

Project-level exceptions.

If project tolerances are to be exceeded, the Project Board no longer has the authority to manage the project. It must escalate this to corporate or programme management for a decision. The Project Board may request the Project Manager to produce an Exception Plan.

Work-Package-level exceptions.

Having agreed on Work Package tolerances with the Team Manager, the Project Manager will be informed of progress through regular Checkpoint Reports.

If a Work Package is forecast to exceed its tolerances, the Team Manager should bring this to the attention of the Project Manager by raising an issue. The Project Manager will advise of any corrective actions if required.

Stage-level exceptions.

Suppose the stage is forecast to exceed its tolerances. In that case, the Project Manager should first produce an Issue Report to capture and analyze the details of the deviation and then provide an Exception Report for the Project Board.

Based on the information in this report, the Project Board may request that the Project Manager produce an Exception Plan to replace the plan forecast to exceed tolerance.

Within the Communication Management Approach, the Project Board can request copies of the Highlight Report be sent to other interested parties outside the project. They may also issue the Highlight Report (or a summary) to Corporate or Programme Management and possibly the End Stage Report.

End Stage Report.

This is produced by the Project Manager towards the end of each management stage, providing the Project Board with information on the progress to date, the overall project situation and, along with the next Stage Plan, sufficient information to ask for a Project Board decision on what to do next with the project.

End Project Report.

This is produced by the Project Manager towards the end of the project, during the Closing a Project process, and is used by the Project Board to evaluate the project and authorize closure.

PRINCE2 Masterclass

Fully compliant with the current PRINCE2 2023 Syllabus

5.0
Prince2 Practitioner Masterclass

Your Route To PRINCE2 Practitioner

Prepare for your PRINCE2 Foundation and Practitioner Exams with our famous on-line course with streaming HD Video Lessons, study guides and mock exams. In the last fifteen years we have had 6,000+ Academy students successfully transform their careers as PRINCE2 Practitioners.

  • Bite Sized Lessons  The sheer size of PRINCE2 can be daunting. The Masterclass will guide you through the syllabus in easy to consume bite sized lessons
  • Be prepared and confident for the exams  Test your knowledge in a fun, entertaining environment with the PRINCE2 Foundation & practitioner exam revision tools
  • Enjoy yourself!  This PRINCE2 Foundation & Practitioner online course is broken into bite-size lessons, combining leading edge multimedia and interactive exercises for optimum enjoyment and knowledge retention
  • Feel confident with full tutorial support  Benefit from fast access to experienced, one-to-one learning support as you study via email and phone, so there is no need to feel isolated while you are learning
  • Take your time  Study at your own pace by bookmarking your progress and picking up where you left off at a speed that suits you

Dave Litten


Dave spent 25+ years as a senior project manager for UK and USA multinationals and has deep experience in project management. He now develops a wide range of Project Management Masterclasses, under the Projex Academy brand name. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.

The Projex Academy

related posts:

{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}

Project Management Masterclasses