.st0{fill:#FFFFFF;}

Foundation Exam Questions Risk and Quality 

 May 19, 2016

By  Dave Litten

PRINCE2 Foundation Exam – example questions and answers

How is the Risk Register used in the Managing a Stage Boundary Process?

  1. Checked for any Issue Reports noted for review at stage end
  2. Reviewed for the status of risks
  3. Updated to record that all risks have been closed
  4. Checked to ensure that all open risks have been transferred to the Issue Register

Which is recommended as a possible risk response type for an opportunity?

  1. Reduce
  2. Transfer
  3. Reject
  4. Fallback

What is risk appetite?

  1. Part of the project budget, used to pay for any additional activities required to manage risks
  2. The funds the Project Board is willing to spend on the management of risk
  3. Permissible deviation from planned expenditure without the need to escalate to the next higher authority
  4. An organization’s attitude towards risk exposure

What is a purpose of the Risk Management Strategy?

  1. Defines the techniques to be used when assessing project threats and opportunities
  2. Summarizes exposure to strategic, programme, project and operational threats and opportunities
  3. Recommends responses for each of the project threats and opportunities
  4. Identifies suitable risk owners for each of the project threats and opportunities

Which term is used to identify when a risk might materialize?

  1. Impact
  2. Proximity
  3. Probability
  4. Evaluate

What is a risk budget used to fund?

  1. Potential changes that may be required as the project progresses
  2. Shortfall in estimating the development costs of the project’s products
  3. Additional activities to reduce, avoid, fallback, transfer, share or enhance project risks
  4. Assessment of project risks and the planning of any responses to deal with these

What is a risk cause?

  1. Negative consequence of a threat occurring
  2. Explanation of the event(s) which, should they occur, would create a problem
  3. Positive consequence of an opportunity exploited
  4. A situation which creates uncertainty

What is the first step within the recommended risk management procedure?

  1. Identify
  2. Assess
  3. Plan
  4. Implement

Which is an objective of the quality review technique?

  1. Involve key interested parties in promoting wider acceptance
  2. Develop and improve the specification of a product through continuous assessment
  3. Correct any typographical errors found in a product and obtain sign-off during the quality review meeting
  4. Update the status information in the configuration Item Record when a product is signed-off

Identify the missing words in the following sentence:

Any requests for change, which require Project Board approval, should be recorded in the [ ? ] and their status monitored by the Project Manager

  1. Product Description
  2. Issue Register
  3. Configuration Item Record
  4. Quality Register

If a product fails its quality check, which management product should always be updated?

  1. Risk Register
  2. Issue Register
  3. Quality Register
  4. Lessons Log

Identify the missing words in the following sentence:

If the Project Manager needs to know the results of a quality review, reviewing the [ ? ] will provide a summary together with the date of any follow-up meeting.

  1. Stage Plan
  2. Issue Register
  3. Daily Log
  4. Quality Register

If a product fails its quality check, which management product should always be updated?

  1. Ensure that all products of the project meet business expectations
  2. Address the procedures and responsibilities for the creation, maintenance and control of project products
  3. Clearly define the method of delivering the project’s products
  4. Enable the assessment of continuing project viability

ANSWERS

How is the Risk Register used in the Managing a Stage Boundary Process?

  1. Checked for any Issue Reports noted for review at stage end
  2. Reviewed for the status of risks
  3. Updated to record that all risks have been closed
  4. Checked to ensure that all open risks have been transferred to the Issue Register

Which is recommended as a possible risk response type for an opportunity?

  1. Reduce
  2. Transfer
  3. Reject
  4. Fallback

What is risk appetite?

  1. Part of the project budget, used to pay for any additional activities required to manage risks
  2. The funds the Project Board is willing to spend on the management of risk
  3. Permissible deviation from planned expenditure without the need to escalate to the next higher authority
  4. An organization’s attitude towards risk exposure

What is a purpose of the Risk Management Strategy?

  1. Defines the techniques to be used when assessing project threats and opportunities
  2. Summarizes exposure to strategic, programme, project and operational threats and opportunities
  3. Recommends responses for each of the project threats and opportunities
  4. Identifies suitable risk owners for each of the project threats and opportunities

Which term is used to identify when a risk might materialize?

  1. Impact
  2. Proximity
  3. Probability
  4. Evaluate

What is a risk budget used to fund?

  1. Potential changes that may be required as the project progresses
  2. Shortfall in estimating the development costs of the project’s products
  3. Additional activities to reduce, avoid, fallback, transfer, share or enhance project risks
  4. Assessment of project risks and the planning of any responses to deal with these

What is a risk cause?

  1. Negative consequence of a threat occurring
  2. Explanation of the event(s) which, should they occur, would create a problem
  3. Positive consequence of an opportunity exploited
  4. A situation which creates uncertainty

What is the first step within the recommended risk management procedure?

  1. Identify
  2. Assess
  3. Plan
  4. Implement

Which is an objective of the quality review technique?

  1. Involve key interested parties in promoting wider acceptance
  2. Develop and improve the specification of a product through continuous assessment
  3. Correct any typographical errors found in a product and obtain sign-off during the quality review meeting
  4. Update the status information in the configuration Item Record when a product is signed-off

Identify the missing words in the following sentence:

Any requests for change, which require Project Board approval, should be recorded in the [ ? ] and their status monitored by the Project Manager

  1. Product Description
  2. Issue Register
  3. Configuration Item Record
  4. Quality Register

If a product fails its quality check, which management product should always be updated?

  1. Risk Register
  2. Issue Register
  3. Quality Register
  4. Lessons Log

Identify the missing words in the following sentence:

If the Project Manager needs to know the results of a quality review, reviewing the [ ? ] will provide a summary together with the date of any follow-up meeting.

  1. Stage Plan
  2. Issue Register
  3. Daily Log
  4. Quality Register

If a product fails its quality check, which management product should always be updated?

  1. Ensure that all products of the project meet business expectations
  2. Address the procedures and responsibilities for the creation, maintenance and control of project products
  3. Clearly define the method of delivering the project’s products
  4. Enable the assessment of continuing project viability

Pass YOUR PRINCE2 Foundation and Practitioner Exams At First Try!

Wanna Get Your Hands On a Sample PRINCE2 Foundation and Practitioner Exam Paper – WITH ANSWERS?

PRINCE2 Masterclass

Fully compliant with the current PRINCE2 2023 Syllabus

5.0
Prince2 Practitioner Masterclass

Your Route To PRINCE2 Practitioner

Prepare for your PRINCE2 Foundation and Practitioner Exams with our famous on-line course with streaming HD Video Lessons, study guides and mock exams. In the last fifteen years we have had 6,000+ Academy students successfully transform their careers as PRINCE2 Practitioners.

  • Bite Sized Lessons  The sheer size of PRINCE2 can be daunting. The Masterclass will guide you through the syllabus in easy to consume bite sized lessons
  • Be prepared and confident for the exams  Test your knowledge in a fun, entertaining environment with the PRINCE2 Foundation & practitioner exam revision tools
  • Enjoy yourself!  This PRINCE2 Foundation & Practitioner online course is broken into bite-size lessons, combining leading edge multimedia and interactive exercises for optimum enjoyment and knowledge retention
  • Feel confident with full tutorial support  Benefit from fast access to experienced, one-to-one learning support as you study via email and phone, so there is no need to feel isolated while you are learning
  • Take your time  Study at your own pace by bookmarking your progress and picking up where you left off at a speed that suits you

Dave Litten


Dave spent 25+ years as a senior project manager for UK and USA multinationals and has deep experience in project management. He now develops a wide range of Project Management Masterclasses, under the Projex Academy brand name. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.

The Projex Academy

related posts:

{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}

Project Management Masterclasses