Foundation Exam Questions – Part1
Which is one of the six aspects of project performance that we wish to manage?
- Performance
- Reliability
- Scope
- Ease of use
Which statement does NOT define a characteristic of a project?
- Has a higher degree of risk than business as usual
- Involves people with different skills introducing a change that will impact others outside of the team
- Has a lifespan that usually covers the delivery of the outputs and the realization of the benefits
- A temporary management structure created for the implementation of business products
Which of the PRINCE2 principles supports the definition of tolerances for the six project objectives?
- Manage by stages
- Tailor to suit the project environment
- Focus on products
- Manage by exception
Which is one of the four integrated elements within PRINCE2?
- Quality
- Role descriptions
- Processes
- Product Description
How does the Starting up a Project process support the “manage by stages” principle?
- Provides a structured set of activities for the pre-project stage of the PRINCE2 journey
- Determines the level of authority delegated to the Project Manager for the initiation stage
- Ensures time is not wasted initiating a project based on unsound assumptions
- Ensures that the work required for project initiation is planned
Which of the following takes place before the initiation of a project?
- Provide the Executive with a role description
- Consider the successes and failures of similar activities carried out in the past
- Record and update all initial risks in the Daily Log
- Develop the detailed Business Case why the project is worth doing
- 1, 2, 3
- 1, 2, 4
- 1, 3, 4
- 2, 3, 4
What is a purpose of the Project Brief?
- Defines the project, to form the basis for its management and the assessment of overall success
- Outlines any lessons from previous projects and how they may affect this project
- Communications the quality techniques and standards to be applied to achieve the required quality levels
- Provides a firm basis on which to initiate the project
Which is a purpose of the Starting up a Project process?
- Ensuring that the prerequisites for initiating the project are in place
- Establishing that the Project Plan can meet the required target dates
- Creating the Project Initiation Documentation so the project can be initiated
- Confirming to corporate or programme management that quality expectations will be met
ANSWERS
Which is one of the six aspects of project performance that we wish to manage?
- Performance
- Reliability
- Scope
- Ease of use
Which statement does NOT define a characteristic of a project?
- Has a higher degree of risk than business as usual
- Involves people with different skills introducing a change that will impact others outside of the team
- Has a lifespan that usually covers the delivery of the outputs and the realization of the benefits
- A temporary management structure created for the implementation of business products
Which of the PRINCE2 principles supports the definition of tolerances for the six project objectives?
- Manage by stages
- Tailor to suit the project environment
- Focus on products
- Manage by exception
Which is one of the four integrated elements within PRINCE2?
- Quality
- Role descriptions
- Processes
- Product Description
How does the Starting up a Project process support the “manage by stages” principle?
- Provides a structured set of activities for the pre-project stage of the PRINCE2 journey
- Determines the level of authority delegated to the Project Manager for the initiation stage
- Ensures time is not wasted initiating a project based on unsound assumptions
- Ensures that the work required for project initiation is planned
Which of the following takes place before the initiation of a project?
- Provide the Executive with a role description
- Consider the successes and failures of similar activities carried out in the past
- Record and update all initial risks in the Daily Log
- Develop the detailed Business Case why the project is worth doing
- 1, 2, 3
- 1, 2, 4
- 1, 3, 4
- 2, 3, 4
What is a purpose of the Project Brief?
- Defines the project, to form the basis for its management and the assessment of overall success
- Outlines any lessons from previous projects and how they may affect this project
- Communications the quality techniques and standards to be applied to achieve the required quality levels
- Provides a firm basis on which to initiate the project
Which is a purpose of the Starting up a Project process?
- Ensuring that the prerequisites for initiating the project are in place
- Establishing that the Project Plan can meet the required target dates
- Creating the Project Initiation Documentation so the project can be initiated
- Confirming to corporate or programme management that quality expectations will be met