Foundation Exam Questions – Part 3
Which of the following is a baseline management product?
- Benefits Management Approach
- Issue Register
- Highlight Report
- Products Status Account
How does the Business Case theme support the continued business justification principle?
- Allows projects not delivering direct benefits to proceed without a Business Case
- Removes the need for a separate Business Case where a project is part of a programme
- Mandates that even the simplest of projects should have a Business Case
- Ensures a new Business Case is created at the end of each stage to confirm the viability of the next stage
What is a purpose of the Benefits Management Approach?
- Documents the justification for the undertaking of a project
- Describes only residual benefits and those that could not be achieved during the lifecycle of the project
- Provides a schedule of activities to measure achievement of those benefits which could not be measured during the project
- Provides the Timescales over which the benefits will be realized, for entry into the Business Case
What would you NOT find in a Business Case?
- Major potential threats to the expected costs and benefits
- Details of the existing situation, how this needs to change and why
- A forecast of what will happen if the project is not approved
- The names of those people responsible for achieving the benefits
Which role is responsible for capturing the customer’s quality expectations?
- Project Manager
- Executive
- Senior Supplier
- Senior User
Which fact is true of Project Assurance but not quality assurance?
- Responsible for monitoring the conduct of the project
- Independent of the Project Manager
- Appointed as part of the project management team
- Responsible for reviewing the project for compliance with corporate standards
Which is a purpose of the Organization theme?
- Establish tolerances around the resources utilized on the project
- Provide project management training to those working within the project
- Establish a structure of accountability and responsibility for the project
- Implement the controls required to permit management by exception
Who represents the ‘delivering’ level on the project management team?
- Project Board
- Project Manager
- Team Manager
- Project Support
Identify the missing words in the following sentence:
If a Project Manager has the appropriate specialist skills and knowledge, there may be no need to appoint [ ? ] to the project.
- Senior Supplier(s)
- Team Manager(s)
- Project Assurance
- Senior User(s)
Which statement is true for project stakeholders?
- Some have decision-making authority within the project environment
- All are external to the corporate organization
- All are internal to the project management team structure
- None have decision-making authority within the project environment
When does PRINCE2 say the project management team should be considered for updating?
- As and when new stakeholders are identified
- When planning a quality review, the producer, reviewer(s), chair and administrator will need to be added
- At the end of each stage, when preparing the Stage Plan for the next stage
- During product creation, if a member of the delivery team is not available and has to be replaced
ANSWERS
Which of the following is a baseline management product?
- Benefits Management Approach
- Issue Register
- Highlight Report
- Products Status Account
How does the Business Case theme support the continued business justification principle?
- Allows projects not delivering direct benefits to proceed without a Business Case
- Removes the need for a separate Business Case where a project is part of a programme
- Mandates that even the simplest of projects should have a Business Case
- Ensures a new Business Case is created at the end of each stage to confirm the viability of the next stage
What is a purpose of the Benefits Management Approach?
- Documents the justification for the undertaking of a project
- Describes only residual benefits and those that could not be achieved during the lifecycle of the project
- Provides a schedule of activities to measure achievement of those benefits which could not be measured during the project
- Provides the Timescales over which the benefits will be realized, for entry into the Business Case
What would you NOT find in a Business Case?
- Major potential threats to the expected costs and benefits
- Details of the existing situation, how this needs to change and why
- A forecast of what will happen if the project is not approved
- The names of those people responsible for achieving the benefits
Which role is responsible for capturing the customer’s quality expectations?
- Project Manager
- Executive
- Senior Supplier
- Senior User
Which fact is true of Project Assurance but not quality assurance?
- Responsible for monitoring the conduct of the project
- Independent of the Project Manager
- Appointed as part of the project management team
- Responsible for reviewing the project for compliance with corporate standards
Which is a purpose of the Organization theme?
- Establish tolerances around the resources utilized on the project
- Provide project management training to those working within the project
- Establish a structure of accountability and responsibility for the project
- Implement the controls required to permit management by exception
Who represents the ‘delivering’ level on the project management team?
- Project Board
- Project Manager
- Team Manager
- Project Support
Identify the missing words in the following sentence:
If a Project Manager has the appropriate specialist skills and knowledge, there may be no need to appoint [ ? ] to the project.
- Senior Supplier(s)
- Team Manager(s)
- Project Assurance
- Senior User(s)
Which statement is true for project stakeholders?
- Some have decision-making authority within the project environment
- All are external to the corporate organization
- All are internal to the project management team structure
- None have decision-making authority within the project environment
When does PRINCE2 say the project management team should be considered for updating?
- As and when new stakeholders are identified
- When planning a quality review, the producer, reviewer(s), chair and administrator will need to be added
- At the end of each stage, when preparing the Stage Plan for the next stage
- During product creation, if a member of the delivery team is not available and has to be replaced