.st0{fill:#FFFFFF;}

Creating the PRINCE2 Specialist Products 

 May 18, 2023

By  Dave Litten

Creating the PRINCE2 Specialist Products

In order to carry out the work of the project, and agreement and authorisation of it must occur between the project manager and the specialist team (usually represented by the team manager).

PRINCE2 provides the work package as the formal document containing the project managers work requirements, information and instructions, and in essence, acts as a ‘contract’ to pass responsibility between the project manager and the team manager who will be actually carrying out the work.

Such work packages are normally used during the delivery stages two pass from the ‘controlling a stage’ process to the ‘managing product delivery’ process.

Each work package contains information on at least one of the specialist products by the inclusion of the ‘product description’ for each of the above products.

PRINCE2 states that work should only commence and continue with the consent of the project manager, and hence the work package including its authorisation and acceptance, is a powerful control for the project.

It is important to recognise that no specialist work of any kind can be carried out unless there is an authorized and agreed a work package covering such work.

For the project manager to maintain sufficient an effective control, the work package allows the team to carry out the work without constantly referring to the project manager which would likely cause delays and deviation from the authorised stage plan.

PRINCE2 Specialist Products Shell – The Work package benefits

The information contained in the work package can be used to cross check estimations made during the planning of the stage, and reviewing them now rather than once the work is underway, will allow such issues to be discussed and potential alternative arrangements or contingency plans to be drawn up.

The following points will have understand the full benefits of a work package:

  • As a mechanism for formally passing work instructions, it helps enormously to avoid any misunderstandings or assumptions
  • Where appropriate, it can be used as an aid for performance assessment of those carrying out the work, by their line manager
  • Because the structure of a work package has been carefully thought through for effective communication, it can form an effective set of information when included within a contract
  • The work package can highlight aspects that need to be communicated to other stakeholders and potential auditing or regulatory issues
  • The work package will contain information on interim products and a milestone dates, including any external dependencies upon which these rely
  • The structure of the work package will ensure the low probability of any aspects of the work being missed all forgotten.

Because the work package is given to the team manager it avoids the team manager having to rely on their memory of the conversation regarding the work, and of course it also helps because the team manager does not need to document the work any further.

The work package contains detailed product descriptions of each product to be created how progress is to be reported, as well as other key aspects to be covered later in this article.  The discipline and information contained within the work package will help be focused discussion between the project manager and team manager, and this will encourage both parties to clarify their understanding and to ensure that the work can be done within the constraints laid down.

It is expected that the work package will normally be handled formally, but if appropriate to do so, the work package can be a verbal instruction from project manager to team manager.

Some of the factors that may influence whether a work package is done formally or informally may include the following aspects:

How complex is the work?  If it is detailed and multifaceted work, or that special instructions are needed to carry out the work, all that detailed information is needed in order to carry out the work, then the work package should consist of written instructions.

The knowledge and skill sets of the specialist team.  If the specialist team are highly experienced with the type of products and the environment within which they will operate, then passing the details verbally may be acceptable.

The work and product creation are well understood.  If the team have previous experience of the work, and it is of a straightforward and simple nature to carry out within a short time frame, then a verbal work package may be acceptable.

Passing work to a third party.  If the products are to be created by a separate organization or group, and most particularly if it forms part of a legal contract, then the work package should take the form of a written record.

The PRINCE2 Work Package composition

Date

This can either be the date of the agreement made between the project manager and team manager, or the date that it is issued.

Team manager or person authorized

This is the identification and who is responsible for delivery of the work and hence the creation of the products.

Work package description

This is a description of the work to be carried out, but should include exactly what is to be achieved from the work of.

Techniques, processes and procedures

This refers to those that will be used to create the specialist products, and should include aspects such as calls, standards, or process.

Development interfaces

This refers to the human interface, and may include those who are providing information as well as those who mainly to receive information

Operations and maintenance interfaces

This section identifies any specialist product linkages, for example if a bottle cap needs to have the same screw thread size, and such data of course relates to such a relationship for its operational life. This section may also refer to existing products outside of this work package, or those to be created by another work package, project, or organization.

Configuration Management requirements

This covers any arrangements to be made by those producing the products for their version control.

This may also describe obtaining copies of any other products, or their product descriptions.  Also it will describe how the product or its details are to be submitted to configuration management, and may describe any storage or security requirements.

Joint agreements

As part of getting the work package contents and constraints agreed with the team manager, this section is where the details are captured of the work effort, cost (if appropriate), key milestones and the start and end dates of individual activities and product creation.

It may be useful to include the team plan, or at least extracts from it under this section.

When the team manager agrees to take on the work package and to execute it within the constraints laid down, then this section plays an important part in making the decision whether or not to accept the work package or ask whether it should be modified in some way.

These joint agreements are particularly important when the work package forms part of the work statement within a legal contract.

Tolerances

The setting of work package tolerance by the project manager is optional.  But if tolerances are to be set they should be stated here along with the type of tolerance (for example cost and time).

Constraints

These of course cover any constraints apart from the already mentioned tolerances.  Constraints could describe just about anything, and may include certain individuals to be used, timing such as milestones or completion dates of products within this work package, charges to be levied for example test house prices, or constraints with regard to certain rules or compliance such as safety measures and security.

Reporting arrangements

This will cover how often the checkpoint reports should occur, how they should occur (for example an e-mail, a formal report, or a meeting).  It should also describe the contents and information contained within the checkpoint report as this may include specific extra data for this particular work package.

Problem handling and escalation

PRINCE2 describes the steps and procedures for raising issues and risks.  This section may just refer to those steps, or tailor them to suit the nature and types of products, including their environment, within this work package.

An organization may have specific extra steps that need to be followed, and specific individuals that need to be involved within issues and risks, all those who need to make decisions due to their authority on such items.

Extracts or references

This may include any extra data, information, or extracts from specific documents.  In particular, such documents might include an extract from the stage plan which may help in putting the work package within context, and also help with identifying either previous work packages or activities, and those that follow from this particular work package.

Product descriptions

A product description for all products to be created within this work package, should be included as a form an important part under the extracts or references section.

Approval method

There are two important approvals to be stated here:

The person, role or group who will approve each completed product within the work package.

However project manager is to be advised both for the products mentioned above, and for completion of the entire work package.

The level of formality that all of the above should follow, will vary from project to project.  At its most informal, the work package may be given verbally although care should be taken to acknowledge key points.

However typically, the work package will be documented in some way, and it is important therefore they should include a record, and even possibly a signature, covering these specific points:

  • Initial authorisation and the date of the work package by the project manager
  • Initial agreement that the work package can and will be carried out by the team manager
  • Agreement by the project manager (or others such as project assurance) as each product is approved
  • Agreement by both the team manager and project manager that the work package is complete

The final two points above may be particularly important if the work package is being performed under a contract, as this may trigger payment milestones to the supplier.  Appropriate reference should first be made with any such contract by for drafting the relevant work package.

Finally, it is worth mentioning that are referenced should be made to the quality management strategy, the configuration management strategy, and the stage plan as part of creating each work package.

Get The Real Deal HERE!

Prince2

PRINCE2 Masterclass

Fully compliant with the current PRINCE2 2023 Syllabus

5.0
Prince2 Practitioner Masterclass

Your Route To PRINCE2 Practitioner

Prepare for your PRINCE2 Foundation and Practitioner Exams with our famous on-line course with streaming HD Video Lessons, study guides and mock exams. In the last fifteen years we have had 6,000+ Academy students successfully transform their careers as PRINCE2 Practitioners.

  • Bite Sized Lessons  The sheer size of PRINCE2 can be daunting. The Masterclass will guide you through the syllabus in easy to consume bite sized lessons
  • Be prepared and confident for the exams  Test your knowledge in a fun, entertaining environment with the PRINCE2 Foundation & practitioner exam revision tools
  • Enjoy yourself!  This PRINCE2 Foundation & Practitioner online course is broken into bite-size lessons, combining leading edge multimedia and interactive exercises for optimum enjoyment and knowledge retention
  • Feel confident with full tutorial support  Benefit from fast access to experienced, one-to-one learning support as you study via email and phone, so there is no need to feel isolated while you are learning
  • Take your time  Study at your own pace by bookmarking your progress and picking up where you left off at a speed that suits you

Dave Litten


Dave spent 25+ years as a senior project manager for UK and USA multinationals and has deep experience in project management. He now develops a wide range of Project Management Masterclasses, under the Projex Academy brand name. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.

The Projex Academy

related posts:

{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}

Project Management Masterclasses