- Pass The PRINCE2 Exam First Time
- PRINCE2 In Bite-Sized Chunks.
- Key Foundation and Practitioner Learning Points - PRINCE2
- Change Management
- Managing and Controlling a PRINCE2 Delivery Stage
- PRINCE2 Project Closure
- PRINCE2 Starting Up A Project Process
- Using PRINCE2 Initiating A Project Process
- PRINCE2 Authorizing Initiation
- The PRINCE2 Controlling a Stage Process
- Appoint The Executive and Project Manager
- Authorising a PRINCE2 Project
- Authorize a Stage or Exception Plan
- Authorize a Work Package
- Capture and Examine Issues and Risks
- Change Control
- Change control procedures
- Configuration Management
- Configuration Management and Change Control
- Controlling a stage
- Create the PRINCE2 Communication Management Strategy
- Creating a PRINCE2 Plan
- Design and appoint the Project Management Team
- Execute a PRINCE2 Work Package
- Give Ad-hoc direction in a PRINCE2 project
- Hand over products and evaluate a PRINCE2 project
- Managing A Stage Boundary
- Managing Product Delivery process
- PRINCE2 - Authorise Project Closure
- PRINCE2 - Directing a Project PRocess
- PRINCE2 Configuration Management and Change Control
- PRINCE2 Controls and Tolerance
- PRINCE2 Estimating Techniques
- PRINCE2 Management Stages
- PRINCE2 Plans
- PRINCE2 Principles
- PRINCE2 Product-based Planning video
- PRINCE2 Product-based planning technique
- PRINCE2 Progress reporting
- PRINCE2 Quality Theme
- Plan The Next Stage or Exception Plan
- Plan the Initiation Stage in PRINCE2
- Prepare the PRINCE2 Quality Management Strategy
- Prepare the Risk Management Strategy
- Prepare the outline Business Case
- Product Based Planning
- Project Board and Project Manager PRINCE2 Controls
- Project Startup
- Quality Expectations and Acceptance Criteria
- Quality Management Strategy
- Quality review technique
- Report Highlights
- Reporting PRINCE2 Stage End
- Select the project approach and assemble the Project Brief
- Set up the PRINCE2 project controls
- Simple Study Aid
- Tailoring PRINCE2 Themes
- Take corrective action
- The Closing a Project Process
- The Controlling a Stage Process
- The Core Seven
- The Only PRINCE2 Sample Practitioner Exam Paper On The Internet!
- The PRINCE2 Business Case
- The PRINCE2 Change Theme
- The PRINCE2 Initiating a project process
- The PRINCE2 Process Sequence
- The PRINCE2 Processes
- The PRINCE2 Quality Review Technique
- The PRINCE2 Risk Management procedure
- The PRINCE2 Themes
- The Prince2 Process Sequence
- The risk management procedure
- prepare for planned or premature closure
- The PRINCE2 Article Library
- 38 Speedy Power Keys For Your PRINCE2 Project Health Check.
- Carrying out a PRINCE2 Quality Check
- The Product Description
- The plans theme and product based planning
- Creating a PRINCE2 Product Description
- PRINCE2 - Keeping Your Project On track - Part 2
- PRINCE2 Article Database
- PRINCE2 – Keeping Your Project On Track – PART 1
- Tailoring PRINCE2 for a feasibility study.
- Tailoring PRINCE2 with Agile (DSDM Atern)
- The Benefits Review Plan
- The PRINCE2 Risk Theme – Uncertainty Mastered!
- The PRINCE2 Work Package
- The Secrets Of tailoring PRINCE2
- The Use and Content of the Issue Register and Issue Report
- Applying earned value calculations to PRINCE2.
- PRINCE2 Foundation and Practitioner Exam Tips
- Using Project Sc ale In A PRINCE2 Project
- Creating a PRINCE2 Exception Report
- Agile verses PRINCE2 - a new species in evolution
- PART TWO of my Configuration Management In PRINCE2 Video
- PRINCE2 Quality
- Real-World PRINCE2 Planning
- Reviewing the progress on a PRINCE2 project
- Risk management
- Things You Might Not Know About PRINCE2
- The PRINCE2 Project Board and Governance
PRINCE2 Project Closure
PRINCE2 Project Closure
A very important point needs to be made here. If the project, within any management stage, needs to be brought to a premature close, then the closing a project process (CP) is used. Let us suppose that a given project has three delivery stages after the initiation stage. In the final delivery stage, work packages containing information on the specialist products to be created will be issued and managed as described above.
However, once the final specialist product within the final work package has been approved, then the project manager will trigger the closing a project (CP) processes to shut the project down in a controlled manner. A final management stage is not used to merely to use the Closing a Project process. In summary, the final stage of a project will use the Controlling a Stage, Managing Product Delivery, and Closing a Project processes.
Assuming a natural close to the project, then the prepare planned closure activity will be used. The project manager would use Project Support as they provide Configuration Management, and request a product status account to ensure that all products within the project would have been approved and that the project acceptance criteria have been met. The Project Plan should be updated with the ‘actuals’ of this final stage.
The projects products must now be handed over to the operational and maintenance environment, where they will be used to ultimately realise the benefits contained as stated within the Business Case. The project manager would updates relevant configuration item records to show that such products have the status of ‘operational’, any acceptance records should be created or obtained, and the Benefits Review Plan updated to reflect any products that have already realized benefits and to include any post project activities for such benefits that have yet to be realized.
The re-evaluate the project activity will create the end of project report to capture actual progress and aspects such as project performance metrics, and will include the Lessons Report based upon the information contained within the Lessons Log.
In the case of premature close, then the reasons for this should be entered and updated on the Issue Register, and if necessary any additional work may be needed to buy the complete unfinished products or to make them safe. Once the project manager has determined that the project should and can be closed, then a recommendation of such should be raised to the project board in the form of a closure recommendation.
The final activity in any project, is the authorize project closure within the Directing a Project process. The project board would need to review original and updated versions of the PID, review and approve the End Project Report, confirm any follow-on actions or loose ends, verify that the projects products have been handed over in an appropriate manner, ensure that the Business Case remains viable, advise that the project can now be closed, and advise those supplier resources that these can now be withdrawn.