- Pass The PRINCE2 Exam First Time
- PRINCE2 In Bite-Sized Chunks.
- Key Foundation and Practitioner Learning Points - PRINCE2
- Change Management
- Managing and Controlling a PRINCE2 Delivery Stage
- PRINCE2 Project Closure
- PRINCE2 Starting Up A Project Process
- Using PRINCE2 Initiating A Project Process
- PRINCE2 Authorizing Initiation
- The PRINCE2 Controlling a Stage Process
- Appoint The Executive and Project Manager
- Authorising a PRINCE2 Project
- Authorize a Stage or Exception Plan
- Authorize a Work Package
- Capture and Examine Issues and Risks
- Change Control
- Change control procedures
- Configuration Management
- Configuration Management and Change Control
- Controlling a stage
- Create the PRINCE2 Communication Management Strategy
- Creating a PRINCE2 Plan
- Design and appoint the Project Management Team
- Execute a PRINCE2 Work Package
- Give Ad-hoc direction in a PRINCE2 project
- Hand over products and evaluate a PRINCE2 project
- Managing A Stage Boundary
- Managing Product Delivery process
- PRINCE2 - Authorise Project Closure
- PRINCE2 - Directing a Project PRocess
- PRINCE2 Configuration Management and Change Control
- PRINCE2 Controls and Tolerance
- PRINCE2 Estimating Techniques
- PRINCE2 Management Stages
- PRINCE2 Plans
- PRINCE2 Principles
- PRINCE2 Product-based Planning video
- PRINCE2 Product-based planning technique
- PRINCE2 Progress reporting
- PRINCE2 Quality Theme
- Plan The Next Stage or Exception Plan
- Plan the Initiation Stage in PRINCE2
- Prepare the PRINCE2 Quality Management Strategy
- Prepare the Risk Management Strategy
- Prepare the outline Business Case
- Product Based Planning
- Project Board and Project Manager PRINCE2 Controls
- Project Startup
- Quality Expectations and Acceptance Criteria
- Quality Management Strategy
- Quality review technique
- Report Highlights
- Reporting PRINCE2 Stage End
- Select the project approach and assemble the Project Brief
- Set up the PRINCE2 project controls
- Simple Study Aid
- Tailoring PRINCE2 Themes
- Take corrective action
- The Closing a Project Process
- The Controlling a Stage Process
- The Core Seven
- The Only PRINCE2 Sample Practitioner Exam Paper On The Internet!
- The PRINCE2 Business Case
- The PRINCE2 Change Theme
- The PRINCE2 Initiating a project process
- The PRINCE2 Process Sequence
- The PRINCE2 Processes
- The PRINCE2 Quality Review Technique
- The PRINCE2 Risk Management procedure
- The PRINCE2 Themes
- The Prince2 Process Sequence
- The risk management procedure
- prepare for planned or premature closure
- The PRINCE2 Article Library
- 38 Speedy Power Keys For Your PRINCE2 Project Health Check.
- Carrying out a PRINCE2 Quality Check
- The Product Description
- The plans theme and product based planning
- Creating a PRINCE2 Product Description
- PRINCE2 - Keeping Your Project On track - Part 2
- PRINCE2 Article Database
- PRINCE2 – Keeping Your Project On Track – PART 1
- Tailoring PRINCE2 for a feasibility study.
- Tailoring PRINCE2 with Agile (DSDM Atern)
- The Benefits Review Plan
- The PRINCE2 Risk Theme – Uncertainty Mastered!
- The PRINCE2 Work Package
- The Secrets Of tailoring PRINCE2
- The Use and Content of the Issue Register and Issue Report
- Applying earned value calculations to PRINCE2.
- PRINCE2 Foundation and Practitioner Exam Tips
- Using Project Sc ale In A PRINCE2 Project
- Creating a PRINCE2 Exception Report
- Agile verses PRINCE2 - a new species in evolution
- PART TWO of my Configuration Management In PRINCE2 Video
- PRINCE2 Quality
- Real-World PRINCE2 Planning
- Reviewing the progress on a PRINCE2 project
- Risk management
- Things You Might Not Know About PRINCE2
- The PRINCE2 Project Board and Governance
The PRINCE2 Initiating A Project Process
How To Use The PRINCE2 Initiating A Project Process
After the Project Board use the activity Authorize initiation, the initiating a project process is used within the initiation management stage and the main deliverable here is the PID itself. The activities within this process echo the contents of the project initiation documentation. It makes sense to first determine the various strategies needed within the project be for detailed planning takes place.
The Risk Management Strategy document is created and the Risk Register is set up to capture and manage any risks throughout the project. Any risks which exist already on the Daily Log would now be transferred to the Risk Register. The Risk Management Strategy defines HOW resource will be managed throughout the project.
The Quality Management Strategy document is created and the Quality Register is set up. This register will typically be empty at this point, as this will contain the planned dates of all quality management activities for the creation of the specialist products, and such dates will not be known until the second Stage Plan is created.
This second stage is always the first delivery stage, so-called because this is the first stage (and possibly also the final stage for small simple projects) where specialist products are to be created. The word specialist products refers to the type of project, for example if the project end product is a new office building, then the specialist products would be for example, the building frame itself, roof and walls, water and electricity services to be implemented, heating and lighting products, office equipment and so on. These should not be confused with the PRINCE2 management products such as the Project Brief, Project Initiation Documentation, reports, and so on.
So you can see that the Quality Register will have the actual dates of the quality checking activities entered during a typical delivery stage.
It is worth mentioning that PRINCE2 does not consider a specialist product as complete, until it has had an independent quality check and an appropriate authorization. As part of the PRINCE2 product based planning technique, a product description for each specialist product is written as part of planning for a particular delivery stage. This Product Description will contain the method and the appropriate measurements required for the product to have ensure the pass its quality check.
The Configuration Management Strategy document is created and the Issue Register is set up. In PRINCE2, an issue can be advice of a new risk, a problem or concern, or a change. There are two types of changes: a request for change which typically comes from the customer and it is a request for a change to what was originally agreed. The second type of change is called an off-specification; typically this would come from the supply side and covers some aspect of the project that although agreed, cannot now be met.
Configuration management may be thought of as version control and as such is closely aligned with how change control (mentioned above) is to be implemented. Typically configuration management will be supplied by the project support role.
The final strategy is the Communication Management Strategy, and is created last because the first three strategies will have communication needs and these can be included at this point. As you can see, all four of the strategies are HOW-TO documents.
The Project Plan can now be created in parallel with setting up the various controls that will be needed throughout the project. Typically these controls focus on those needed at project board level for example end stage assessment timing, and the frequency of their regular Highlight Reports, while at project manager level for example, the formality or otherwise of issuing Work Packages and the frequency of the regular Checkpoint Reports.
Highlight Reports cover progress within the management stage, and Checkpoint Reports cover the progress of specialist product creation within a Work Package.
As with all plans, the Project Plan is a document, and will use the PRINCE2 product-based planning technique.
Traditional project planning would start with the brainstorming of the various activities. But one of the principles of PRINCE2 is product focus. What this means is that the product based planning technique starts with the identification of products, initially at the highest level within a project, by creating the Project Product Description, but then going on to create a Product Breakdown Structure which is a hierarchical diagram of the products within a given project.
The next step would be to create Product Descriptions for all appropriate lower level products, including their quality criteria. The final product based planning step is to create a Product flow Diagram, which shows the sequence of creation of the products.
In case you are confused, an activity would normally be described with a noun and verb such as ‘create report’, whereas a product would be described with a noun or outcome for example ‘specification document’.
Within PRINCE2, the next steps cover traditional planning techniques, first identifying the activities needed to create each product, then estimating such activities, creating the schedule or sequence of such activities (usually shown as a network diagram or Gantt Chart view). Then going on to identify risks, their associated response activities, and finally adding the narrative of the plan document.
Because of this, new Product Descriptions along with their quality criteria will be created along with a Configuration Item Record (CIR) for each product. This record forms part of the data and the status for each product held within configuration management.
Also at this point the Project Product Description may now needs to be further refined, for example, as better data is understood for the acceptance criteria of the project end product.
The detailed Business Case can now be developed using the refine the business case activity, as it will use timescale and cost information derived from the Project Plan. This detailed Business Case will be used throughout the project in particular at the end of each management stage where it is updated and used as a basis to proceed or otherwise by the project board.
A new management product is now created based upon some information contained within the business case, and it is called the Benefits Review Plan. As the name suggests, this contains a description of each future benefit, its timing, measurement, and the resources required to carry this out. The Benefits Review Plan is kept separate from the Project Initiation Documentation as it will be used after the project has finished to continue and track the remaining benefits until their eventual realization.
All of the above can now be assembled and forms the Project Initiation Documentation. The project manager will now request that the project board authorize the project. They will use this named activity within the Directing a Project process (DP), and this will always be the first end stage assessment where the reporting stage end will be used within any PRINCE2 project (as the initiation stage is always the first management stage in a PRINCE2 project).



