- Pass The PRINCE2 Exam First Time
- PRINCE2 In Bite-Sized Chunks.
- Key Foundation and Practitioner Learning Points - PRINCE2
- Change Management
- Managing and Controlling a PRINCE2 Delivery Stage
- PRINCE2 Project Closure
- PRINCE2 Starting Up A Project Process
- Using PRINCE2 Initiating A Project Process
- PRINCE2 Authorizing Initiation
- The PRINCE2 Controlling a Stage Process
- Appoint The Executive and Project Manager
- Authorising a PRINCE2 Project
- Authorize a Stage or Exception Plan
- Authorize a Work Package
- Capture and Examine Issues and Risks
- Change Control
- Change control procedures
- Configuration Management
- Configuration Management and Change Control
- Controlling a stage
- Create the PRINCE2 Communication Management Strategy
- Creating a PRINCE2 Plan
- Design and appoint the Project Management Team
- Execute a PRINCE2 Work Package
- Give Ad-hoc direction in a PRINCE2 project
- Hand over products and evaluate a PRINCE2 project
- Managing A Stage Boundary
- Managing Product Delivery process
- PRINCE2 - Authorise Project Closure
- PRINCE2 - Directing a Project PRocess
- PRINCE2 Configuration Management and Change Control
- PRINCE2 Controls and Tolerance
- PRINCE2 Estimating Techniques
- PRINCE2 Management Stages
- PRINCE2 Plans
- PRINCE2 Principles
- PRINCE2 Product-based Planning video
- PRINCE2 Product-based planning technique
- PRINCE2 Progress reporting
- PRINCE2 Quality Theme
- Plan The Next Stage or Exception Plan
- Plan the Initiation Stage in PRINCE2
- Prepare the PRINCE2 Quality Management Strategy
- Prepare the Risk Management Strategy
- Prepare the outline Business Case
- Product Based Planning
- Project Board and Project Manager PRINCE2 Controls
- Project Startup
- Quality Expectations and Acceptance Criteria
- Quality Management Strategy
- Quality review technique
- Report Highlights
- Reporting PRINCE2 Stage End
- Select the project approach and assemble the Project Brief
- Set up the PRINCE2 project controls
- Simple Study Aid
- Tailoring PRINCE2 Themes
- Take corrective action
- The Closing a Project Process
- The Controlling a Stage Process
- The Core Seven
- The Only PRINCE2 Sample Practitioner Exam Paper On The Internet!
- The PRINCE2 Business Case
- The PRINCE2 Change Theme
- The PRINCE2 Initiating a project process
- The PRINCE2 Process Sequence
- The PRINCE2 Processes
- The PRINCE2 Quality Review Technique
- The PRINCE2 Risk Management procedure
- The PRINCE2 Themes
- The Prince2 Process Sequence
- The risk management procedure
- prepare for planned or premature closure
- The PRINCE2 Article Library
- 38 Speedy Power Keys For Your PRINCE2 Project Health Check.
- Carrying out a PRINCE2 Quality Check
- The Product Description
- The plans theme and product based planning
- Creating a PRINCE2 Product Description
- PRINCE2 - Keeping Your Project On track - Part 2
- PRINCE2 Article Database
- PRINCE2 – Keeping Your Project On Track – PART 1
- Tailoring PRINCE2 for a feasibility study.
- Tailoring PRINCE2 with Agile (DSDM Atern)
- The Benefits Review Plan
- The PRINCE2 Risk Theme – Uncertainty Mastered!
- The PRINCE2 Work Package
- The Secrets Of tailoring PRINCE2
- The Use and Content of the Issue Register and Issue Report
- Applying earned value calculations to PRINCE2.
- PRINCE2 Foundation and Practitioner Exam Tips
- Using Project Sc ale In A PRINCE2 Project
- Creating a PRINCE2 Exception Report
- Agile verses PRINCE2 - a new species in evolution
- PART TWO of my Configuration Management In PRINCE2 Video
- PRINCE2 Quality
- Real-World PRINCE2 Planning
- Reviewing the progress on a PRINCE2 project
- Risk management
- Things You Might Not Know About PRINCE2
- The PRINCE2 Project Board and Governance
PRINCE2 Estimating Techniques
PRINCE2 In Bite Sized Chunks.
PRINCE2 Estimating techniques
Delphi technique. This relies on obtaining group input for ideas and problem solving without requiring face-to-face participation. It uses a series of questionnaires interspersed with information summaries and feedback from preceding responses to achieve an estimate.

Bottom-up estimating. Each individual piece of work is estimated on its own merit. These are then summed together to find the estimated efforts for the various summary level activities and overall planParametric estimating Basing estimates on measured/empirical data where possible (for example, estimating models exist in the construction industry that predict materials, effort and duration based on the specification of a building)
Single-point estimating. The use of sample data to calculate a single value which is to serve as a ’best guess’ for the duration of an activity
Comparative estimating. Much data exist about the effort required and the duration of particular items of work. Overtime an organization may build up its own historical data regarding projects that it has undertaken (previous experience or lessons learned).
Where such data exists, it may be useful to reference it for similar projects and apply that data to the estimates
Top-down estimating. Once a good overall estimate has been arrived at for the plan (by whatever means), it can be subdivided through the levels of the product breakdown structure.
By way of example, historically development may be 60% of the total and testing may be 30%. Subdivide development and testing into their components and apportion the effort accordingly
Three-point estimating. Ask appropriately skilled resources for their best-case, most likely and worst-case estimates. The value that the Project Manager should choose is the weighted average of these three estimates
Top-down and bottom-up approach. An overall estimate is calculated for the plan. Individual estimates are then calculated, or drawn from previous plans, to represent the relative weights of the tasks.
The overall estimate is then apportioned across the various summary and detailed-level tasks using the bottom-up figures as weights
Basic rules for estimating:Many books and software packages include some basic rules to help ensure that an accurate and realistic estimate is produced. Examples of such planning rules include:
Always estimate the work effort and then estimate the duration based on the number of resources available to do the work.
Always build in provision for problem solving, meetings and other unexpected events. Cost each activity rather than trying to cost the plan as a whole. Communicate any assumptions, exclusions or constraints you have to the user.
Other examples are:
Assume that resources will only be productive for, say, 75% of their time. Resources working on multiple projects take longer to complete tasks because of time lost switching between them. People are generally optimistic and often underestimate how long tasks will take.
Make use of other people’s experiences and your own. Ensure that the person responsible for creating the product is also responsible for creating the effort estimates
For More Information CLICK HERE



