- Pass The PRINCE2 Exam First Time
- PRINCE2 In Bite-Sized Chunks.
- Key Foundation and Practitioner Learning Points - PRINCE2
- Change Management
- Managing and Controlling a PRINCE2 Delivery Stage
- PRINCE2 Project Closure
- PRINCE2 Starting Up A Project Process
- Using PRINCE2 Initiating A Project Process
- PRINCE2 Authorizing Initiation
- The PRINCE2 Controlling a Stage Process
- Appoint The Executive and Project Manager
- Authorising a PRINCE2 Project
- Authorize a Stage or Exception Plan
- Authorize a Work Package
- Capture and Examine Issues and Risks
- Change Control
- Change control procedures
- Configuration Management
- Configuration Management and Change Control
- Controlling a stage
- Create the PRINCE2 Communication Management Strategy
- Creating a PRINCE2 Plan
- Design and appoint the Project Management Team
- Execute a PRINCE2 Work Package
- Give Ad-hoc direction in a PRINCE2 project
- Hand over products and evaluate a PRINCE2 project
- Managing A Stage Boundary
- Managing Product Delivery process
- PRINCE2 - Authorise Project Closure
- PRINCE2 - Directing a Project PRocess
- PRINCE2 Configuration Management and Change Control
- PRINCE2 Controls and Tolerance
- PRINCE2 Estimating Techniques
- PRINCE2 Management Stages
- PRINCE2 Plans
- PRINCE2 Principles
- PRINCE2 Product-based Planning video
- PRINCE2 Product-based planning technique
- PRINCE2 Progress reporting
- PRINCE2 Quality Theme
- Plan The Next Stage or Exception Plan
- Plan the Initiation Stage in PRINCE2
- Prepare the PRINCE2 Quality Management Strategy
- Prepare the Risk Management Strategy
- Prepare the outline Business Case
- Product Based Planning
- Project Board and Project Manager PRINCE2 Controls
- Project Startup
- Quality Expectations and Acceptance Criteria
- Quality Management Strategy
- Quality review technique
- Report Highlights
- Reporting PRINCE2 Stage End
- Select the project approach and assemble the Project Brief
- Set up the PRINCE2 project controls
- Simple Study Aid
- Tailoring PRINCE2 Themes
- Take corrective action
- The Closing a Project Process
- The Controlling a Stage Process
- The Core Seven
- The Only PRINCE2 Sample Practitioner Exam Paper On The Internet!
- The PRINCE2 Business Case
- The PRINCE2 Change Theme
- The PRINCE2 Initiating a project process
- The PRINCE2 Process Sequence
- The PRINCE2 Processes
- The PRINCE2 Quality Review Technique
- The PRINCE2 Risk Management procedure
- The PRINCE2 Themes
- The Prince2 Process Sequence
- The risk management procedure
- prepare for planned or premature closure
- The PRINCE2 Article Library
- 38 Speedy Power Keys For Your PRINCE2 Project Health Check.
- Carrying out a PRINCE2 Quality Check
- The Product Description
- The plans theme and product based planning
- Creating a PRINCE2 Product Description
- PRINCE2 - Keeping Your Project On track - Part 2
- PRINCE2 Article Database
- PRINCE2 – Keeping Your Project On Track – PART 1
- Tailoring PRINCE2 for a feasibility study.
- Tailoring PRINCE2 with Agile (DSDM Atern)
- The Benefits Review Plan
- The PRINCE2 Risk Theme – Uncertainty Mastered!
- The PRINCE2 Work Package
- The Secrets Of tailoring PRINCE2
- The Use and Content of the Issue Register and Issue Report
- Applying earned value calculations to PRINCE2.
- PRINCE2 Foundation and Practitioner Exam Tips
- Using Project Sc ale In A PRINCE2 Project
- Creating a PRINCE2 Exception Report
- Agile verses PRINCE2 - a new species in evolution
- PART TWO of my Configuration Management In PRINCE2 Video
- PRINCE2 Quality
- Real-World PRINCE2 Planning
- Reviewing the progress on a PRINCE2 project
- Risk management
- Things You Might Not Know About PRINCE2
- The PRINCE2 Project Board and Governance
PRINCE2 Controls and Tolerance
PRINCE2 Progress controls.
For project progress to be measurable, we need to monitor and compare actual achievements against those planned and in this way provide a forecast for the project objectives and continued viability. If this forecast is not favourable then some form of corrective action is needed to bring the project back on track.
There are three PRINCE2 principles at work here, managing by stages, continued business justification and management exception.
When using management by exception, tolerances are set to establish the limits of delegated authority so that each management level knows that while tolerance is forecast NOT to be exceeded, they can take any appropriate actions, but directly tolerance is forecast to be exceeded, then it must be escalated up to the next level for approval. The Progress Theme provides the mechanisms to monitor progress against the allowed tolerances, and the controls to escalate to the next level should any forecast suggests that tolerances will be exceeded.
There is a very specific discipline for management to maintain full control of progress, and it is carried out in a series of simple steps:
• Create and get approved the relevant level of plan
• Give out work and monitor progress
• Compare actual progress against the plan
• Based on actual progress, forecast the future situation
• Review options against future situation
• Detect problems and identify risks
• Initiate corrective action is needed
• Authorise further work
PRINCE2 applies management by exception, and to do so therefore sets tolerances. An exception is a situation where it can be forecast that there will be a deviation beyond the agreed tolerance levels.
These levels are the permissible deviation is above and below a planned target. If they are forecast to be exceeded then this situation must be escalated to the next level of management.
Without tolerances there can be no understanding of when to escalate a situation. For example, if every small deviation from plan was escalated to the project board, then they are doing the project manager’s job who in turn, is only monitoring work and not taking any corrective action.
At the other extreme, if the project manager implements corrective actions well beyond their remit, then when the project board discover what has happened they may question why they were not involved earlier. With agreed tolerance levels, this level of discretion is clearly understood by each level of management.There are six areas of tolerance that can be applied either singly or in any combination and at four possible levels. The four levels are project level tolerances, stage level tolerances, work package level tolerances, and product level tolerances. Work package tolerances are optional.
The following tolerance areas can be set at project, stage and work package levels: Time, cost and scope. Risk tolerance can be set at project level within the Risk Management Strategy document, and within the stage plan or work packages.
Quality tolerance can only be set within the Project Product Description and Product Descriptions. Benefit tolerance can only be set within the Business Case.
For more information on PRINCE2 - GO HERE



