PRINCE2 Controls and Tolerance

 

PRINCE2 Progress controls.

 
For project progress to be measurable, we need to monitor and compare actual achievements against those planned and in this way provide a forecast for the project objectives and continued viability.  If this forecast is not favourable then some form of corrective action is needed to bring the project back on track.  
 
There are three PRINCE2 principles at work here, managing by stages, continued business justification and management exception.
 
prince2 progress controlsWhen using management by exception, tolerances are set to establish the limits of delegated authority so that each management level knows that while tolerance is forecast NOT to be exceeded, they can take any appropriate actions, but directly tolerance is forecast to be exceeded, then it must be escalated up to the next level for approval.  
 
The Progress Theme provides the mechanisms to monitor progress against the allowed tolerances, and the controls to escalate to the next level should any forecast suggests that tolerances will be exceeded.
 
There is a very specific discipline for management to maintain full control of progress, and it is carried out in a series of simple steps:
 
•  Create and get approved the relevant level of plan
 Give out work and monitor progress
 Compare actual progress against the plan
 Based on actual progress, forecast the future situation
 Review options against future situation
 Detect problems and identify risks
 Initiate corrective action is needed
 Authorise further work
 
PRINCE2 applies management by exception, and to do so therefore sets tolerances.  An exception is a situation where it can be forecast that there will be a deviation beyond the agreed tolerance levels.  
 
These levels are the permissible deviation is above and below a planned target.  If they are forecast to be exceeded then this situation must be escalated to the next level of management.
 
Without tolerances there can be no understanding of when to escalate a situation.  For example, if every small deviation from plan was escalated to the project board, then they are doing the project manager’s job who in turn, is only monitoring work and not taking any corrective action.  
 
prince2 controlsAt the other extreme, if the project manager implements corrective actions well beyond their remit, then when the project board discover what has happened they may question why they were not involved earlier.  With agreed tolerance levels, this level of discretion is clearly understood by each level of management.
 
There are six areas of tolerance that can be applied either singly or in any combination and at four possible levels.  The four levels are project level tolerances, stage level tolerances, work package level tolerances, and product level tolerances.  Work package tolerances are optional.
 
The following tolerance areas can be set at project, stage and work package levels: Time, cost and scope.  Risk tolerance can be set at project level within the Risk Management Strategy document, and within the stage plan or work packages.  
 
Quality tolerance can only be set within the Project Product Description and Product Descriptions. Benefit tolerance can only be set within the Business Case.
 
For more information on PRINCE2 -  GO HERE