- Pass The PRINCE2 Exam First Time
- PRINCE2 In Bite-Sized Chunks.
- Key Foundation and Practitioner Learning Points - PRINCE2
- Change Management
- Managing and Controlling a PRINCE2 Delivery Stage
- PRINCE2 Project Closure
- PRINCE2 Starting Up A Project Process
- Using PRINCE2 Initiating A Project Process
- PRINCE2 Authorizing Initiation
- The PRINCE2 Controlling a Stage Process
- Appoint The Executive and Project Manager
- Authorising a PRINCE2 Project
- Authorize a Stage or Exception Plan
- Authorize a Work Package
- Capture and Examine Issues and Risks
- Change Control
- Change control procedures
- Configuration Management
- Configuration Management and Change Control
- Controlling a stage
- Create the PRINCE2 Communication Management Strategy
- Creating a PRINCE2 Plan
- Design and appoint the Project Management Team
- Execute a PRINCE2 Work Package
- Give Ad-hoc direction in a PRINCE2 project
- Hand over products and evaluate a PRINCE2 project
- Managing A Stage Boundary
- Managing Product Delivery process
- PRINCE2 - Authorise Project Closure
- PRINCE2 - Directing a Project PRocess
- PRINCE2 Configuration Management and Change Control
- PRINCE2 Controls and Tolerance
- PRINCE2 Estimating Techniques
- PRINCE2 Management Stages
- PRINCE2 Plans
- PRINCE2 Principles
- PRINCE2 Product-based Planning video
- PRINCE2 Product-based planning technique
- PRINCE2 Progress reporting
- PRINCE2 Quality Theme
- Plan The Next Stage or Exception Plan
- Plan the Initiation Stage in PRINCE2
- Prepare the PRINCE2 Quality Management Strategy
- Prepare the Risk Management Strategy
- Prepare the outline Business Case
- Product Based Planning
- Project Board and Project Manager PRINCE2 Controls
- Project Startup
- Quality Expectations and Acceptance Criteria
- Quality Management Strategy
- Quality review technique
- Report Highlights
- Reporting PRINCE2 Stage End
- Select the project approach and assemble the Project Brief
- Set up the PRINCE2 project controls
- Simple Study Aid
- Tailoring PRINCE2 Themes
- Take corrective action
- The Closing a Project Process
- The Controlling a Stage Process
- The Core Seven
- The Only PRINCE2 Sample Practitioner Exam Paper On The Internet!
- The PRINCE2 Business Case
- The PRINCE2 Change Theme
- The PRINCE2 Initiating a project process
- The PRINCE2 Process Sequence
- The PRINCE2 Processes
- The PRINCE2 Quality Review Technique
- The PRINCE2 Risk Management procedure
- The PRINCE2 Themes
- The Prince2 Process Sequence
- The risk management procedure
- prepare for planned or premature closure
- The PRINCE2 Article Library
- 38 Speedy Power Keys For Your PRINCE2 Project Health Check.
- Carrying out a PRINCE2 Quality Check
- The Product Description
- The plans theme and product based planning
- Creating a PRINCE2 Product Description
- PRINCE2 - Keeping Your Project On track - Part 2
- PRINCE2 Article Database
- PRINCE2 – Keeping Your Project On Track – PART 1
- The PRINCE2 Risk Theme – Uncertainty Mastered!
- The PRINCE2 Work Package
- The Secrets Of tailoring PRINCE2
- The Use and Content of the Issue Register and Issue Report
- PRINCE2 Foundation and Practitioner Exam Tips
- Agile verses PRINCE2 - a new species in evolution
- PART TWO of my Configuration Management In PRINCE2 Video
- PRINCE2 Quality
- Real-World PRINCE2 Planning
- Reviewing the progress on a PRINCE2 project
- Risk management
- Things You Might Not Know About PRINCE2
- The PRINCE2 Project Board and Governance
PRINCE2 Change Management
How To Apply PRINCE2 Change management.
It has been said that for projects, change is inevitable whether it comes from within the project or from external sources. For these reasons, whenever change occurs, it makes sense to have an agreed logical process that allows the project to identify, assess and control any potential and approved changes to the original baselines that where originally agreed for the project.
So what is needed is a systematic and common approach. Once the project plan and other key associated documents have been approved, these become the project "baselines" and can only be changed after approval by the appropriate authority -- normally the project board. Change control is not there to prevent changes, but to ensure that every change is agreed by the relevant authority before implementation.
An important and vital element is the projects use of change control and configuration management (CM). All products that the project produces is subject to configuration management, this includes management documentation as well as specialist products and deliverables. It is important therefore to integrate the use of change control procedures with the configuration management strategy document and the system used by the project.
The system that is set up to manage change should also include the management of the general issues, and in particular how to capture issues and risks. An Issue Register should be set up early in the project to capture and assist in the management of change and issues. A configuration management strategy document must be created as part of planning and this defines the way in which changes and issues are to be managed and handled throughout the project.
The difference between an issue and a risk is that the issue has already happened, whereas a risk is something that may or may not happen -- at some point in the future.
Whenever an issue is raised, it may be managed informally -- usually by the project manager, however if it is to be managed formally then the project manager would enter it into the issue register before proceeding any further. The PRINCE2 methodology status that and Issue Report is created in tandem and contains supplementary information regarding that particular issue.
Changes come in two flavours:
A Request For Change (RFC) which comes from the customer or user and is a request to change one of the project baselines in some way. If there are any extra costs involved in implementing the RFC, then the customer would normally pay for it. Since all RFC's are a change to what had been originally agreed, it is normally the project board alone, who have the authority to agree such changes.
Off Specification. These are normally raised from the supply -- side of the project, and detail some aspect that should be provided by the project, but currently is not - or is forecast not to be, provided. This might include products or deliverables that are missing, or a product not meeting its specification or quality criteria.
At the beginning of a project it needs to be decided how changes and issues are to be prioritised, and it is usual that a ratings system might include terms such as, Must Have, Should Have, Could Have, or Won't Have For Now. For obvious reasons, this is known as Moscow. Such definitions need to be agreed.
Another aspect that needs to be decided is whether or not the project board or senior management wanted to be involved in reviewing all project changes. If many changes are predicted then it may make sense for the project board to appoint a Change Authority who would make decisions on such changes on behalf of the project board. In such cases, the “rules of engagement" needs to be determined.
For example, the change authority would only deal with low cost changes. Another aspect is setting up a change budget for the change of authority to use to fund any approved changes and their implementation. Such additional budgets should be captured within the project plan before sign off. However, a change budget may be set up even if the Project Board decide to deal with changes themselves, as it provides better control when dealing with such changes, and gives clarity to the management of the main project budget.
Here then, is the change control procedure itself...
First. Whenever a change or issue is raised, it should be categorised and entered in the issue/change register.
Second. An impact analysis should now be carried out, and will normally involve relevant specialist team members.
The impact analysis should consider the change or issue impact (which may be positive or negative) on a variety of projects aspects such as:
- Time
- Cost
- Quality
- Scope
- Business Case
- Benefits
- Risk
The change or issue should be prioritised, first, by the originator, and second, after impact analysis. It is important when carrying out the above impact analysis, that representatives from the project business area, the users of the end products, and those who are supplying resources to the project -- are fully involved so that a balanced decision can be reached.
Third. Having understood the full impact of the change or issue, the next step is to consider alternative options and proposing the best actions to take in order to resolve the issue or implement the change. A balanced view is needed and consideration should be given all these options on the projects duration, cost, quality, scope, benefit, and risk performance targets. The advantages gained should be balanced against the impact of implementing the issue or change.
Fourth. A decision is now needed whether or not to implement the issue will change. For a request for change, this would normally need escalating to the project board for their decision, whereas an Off-Specification may be decided by the project manager if they have sufficient authority.
In all PRINCE2 projects, it is a principle that they will use Management By Exception where tolerance boundaries have been set, then should any proposed implementation deviate beyond these tolerances, the project board must be involved in the decision whether to implement or not.
During implementation, the project manager should ensure that its status is reported to the project board up to the point when the issue or change has been fully implemented.



