- Pass The PRINCE2 Exam First Time
- PRINCE2 In Bite-Sized Chunks.
- Key Foundation and Practitioner Learning Points - PRINCE2
- Change Management
- Managing and Controlling a PRINCE2 Delivery Stage
- PRINCE2 Project Closure
- PRINCE2 Starting Up A Project Process
- Using PRINCE2 Initiating A Project Process
- PRINCE2 Authorizing Initiation
- The PRINCE2 Controlling a Stage Process
- Appoint The Executive and Project Manager
- Authorising a PRINCE2 Project
- Authorize a Stage or Exception Plan
- Authorize a Work Package
- Capture and Examine Issues and Risks
- Change Control
- Change control procedures
- Configuration Management
- Configuration Management and Change Control
- Controlling a stage
- Create the PRINCE2 Communication Management Strategy
- Creating a PRINCE2 Plan
- Design and appoint the Project Management Team
- Execute a PRINCE2 Work Package
- Give Ad-hoc direction in a PRINCE2 project
- Hand over products and evaluate a PRINCE2 project
- Managing A Stage Boundary
- Managing Product Delivery process
- PRINCE2 - Authorise Project Closure
- PRINCE2 - Directing a Project PRocess
- PRINCE2 Configuration Management and Change Control
- PRINCE2 Controls and Tolerance
- PRINCE2 Estimating Techniques
- PRINCE2 Management Stages
- PRINCE2 Plans
- PRINCE2 Principles
- PRINCE2 Product-based Planning video
- PRINCE2 Product-based planning technique
- PRINCE2 Progress reporting
- PRINCE2 Quality Theme
- Plan The Next Stage or Exception Plan
- Plan the Initiation Stage in PRINCE2
- Prepare the PRINCE2 Quality Management Strategy
- Prepare the Risk Management Strategy
- Prepare the outline Business Case
- Product Based Planning
- Project Board and Project Manager PRINCE2 Controls
- Project Startup
- Quality Expectations and Acceptance Criteria
- Quality Management Strategy
- Quality review technique
- Report Highlights
- Reporting PRINCE2 Stage End
- Select the project approach and assemble the Project Brief
- Set up the PRINCE2 project controls
- Simple Study Aid
- Tailoring PRINCE2 Themes
- Take corrective action
- The Closing a Project Process
- The Controlling a Stage Process
- The Core Seven
- The Only PRINCE2 Sample Practitioner Exam Paper On The Internet!
- The PRINCE2 Business Case
- The PRINCE2 Change Theme
- The PRINCE2 Initiating a project process
- The PRINCE2 Process Sequence
- The PRINCE2 Processes
- The PRINCE2 Quality Review Technique
- The PRINCE2 Risk Management procedure
- The PRINCE2 Themes
- The Prince2 Process Sequence
- The risk management procedure
- prepare for planned or premature closure
- The PRINCE2 Article Library
- 38 Speedy Power Keys For Your PRINCE2 Project Health Check.
- Carrying out a PRINCE2 Quality Check
- The Product Description
- The plans theme and product based planning
- Creating a PRINCE2 Product Description
- PRINCE2 - Keeping Your Project On track - Part 2
- PRINCE2 Article Database
- PRINCE2 – Keeping Your Project On Track – PART 1
- The PRINCE2 Risk Theme – Uncertainty Mastered!
- The PRINCE2 Work Package
- The Secrets Of tailoring PRINCE2
- The Use and Content of the Issue Register and Issue Report
- PRINCE2 Foundation and Practitioner Exam Tips
- Agile verses PRINCE2 - a new species in evolution
- PART TWO of my Configuration Management In PRINCE2 Video
- PRINCE2 Quality
- Real-World PRINCE2 Planning
- Reviewing the progress on a PRINCE2 project
- Risk management
- Things You Might Not Know About PRINCE2
- The PRINCE2 Project Board and Governance
Give Ad-hoc direction in a PRINCE2 project
Give ad hoc direction.
The project board’s main job is to give direction and authorisation at key points throughout the project. However, there is a need for general communication both from and to the project board at appropriate times during the project. This is the purpose of the ‘Give ad hoc direction’ activity.

It is intended to be an informal mechanism where the project board can offer informal guidance or respond to requests for advice throughout the project.
This activity will be particularly frequent during the initiation stage, and as the project approaches stage boundaries (for example when the project manager is creating the next stage plan and updating other key documents, the project board or project assurance will be frequently involved).
Ad hoc direction may be given or used by an individual member of the project board or collectively from all project board members. Examples of situations that may trigger ad hoc direction include, responding to requests, clarification, conflict resolution, responding to reports or external influences, individual concerns, or responding to changes.
Ad hoc direction is also used for corporate to seek information or give direction, and the project board to communicate with them for similar circumstances.
The project board may appoint project assurance to undertake some of the reviewing, in which case ad hoc direction would be used by project assurance.
There are five general situations in which Give ad hoc direction may be used:
1. In response to informal requests for advice and guidance, normally from the project manager but it may also be from corporate or programme management
2. In response to an escalated Issue Report. The project board’s action will depend on the nature of the issue: if it is a problem or a concern, the project board might ask for an Exception Plan or provide guidance to the project manager.
If it is a Request For Change, the project board may approve it, defer it, reject it, or ask for more information. For an Off Specification, they may grant a concession, defer it, reject it, or ask for more information.
3. If the project manager has raised an Exception Report, the project board may choose to seek advice from corporate or programme management, increase the tolerances that are currently forecast to be exceeded, ask for an exception plan, defer the exception for a stated period of time, or instruct the project manager to close the project prematurely.
4. If the project board have received a Highlight Report, then their actions may be: review the Highlight Report, ensure that the stage is progressing to plan, keep other key stakeholders informed as stated in the Communication Management Strategy document, or ask the project manager to produce an Issue Report and/or an Exception Report.
5. The project board may need to respond from advice and decisions given by corporate or programme management, in which case they will ensure that the project management team is kept informed and notify the project manager should any changes are being requested from corporate or programme management. They may therefore raise an issue, ask for an Exception Plan, or instruct that the project the close the project prematurely. Any of these instructions will be carried out by the project manager.
For more information CLICK HERE



