- Pass The PRINCE2 Exam First Time
- PRINCE2 In Bite-Sized Chunks.
- Key Foundation and Practitioner Learning Points - PRINCE2
- Change Management
- Managing and Controlling a PRINCE2 Delivery Stage
- PRINCE2 Project Closure
- PRINCE2 Starting Up A Project Process
- Using PRINCE2 Initiating A Project Process
- PRINCE2 Authorizing Initiation
- The PRINCE2 Controlling a Stage Process
- Appoint The Executive and Project Manager
- Authorising a PRINCE2 Project
- Authorize a Stage or Exception Plan
- Authorize a Work Package
- Capture and Examine Issues and Risks
- Change Control
- Change control procedures
- Configuration Management
- Configuration Management and Change Control
- Controlling a stage
- Create the PRINCE2 Communication Management Strategy
- Creating a PRINCE2 Plan
- Design and appoint the Project Management Team
- Execute a PRINCE2 Work Package
- Give Ad-hoc direction in a PRINCE2 project
- Hand over products and evaluate a PRINCE2 project
- Managing A Stage Boundary
- Managing Product Delivery process
- PRINCE2 - Authorise Project Closure
- PRINCE2 - Directing a Project PRocess
- PRINCE2 Configuration Management and Change Control
- PRINCE2 Controls and Tolerance
- PRINCE2 Estimating Techniques
- PRINCE2 Management Stages
- PRINCE2 Plans
- PRINCE2 Principles
- PRINCE2 Product-based Planning video
- PRINCE2 Product-based planning technique
- PRINCE2 Progress reporting
- PRINCE2 Quality Theme
- Plan The Next Stage or Exception Plan
- Plan the Initiation Stage in PRINCE2
- Prepare the PRINCE2 Quality Management Strategy
- Prepare the Risk Management Strategy
- Prepare the outline Business Case
- Product Based Planning
- Project Board and Project Manager PRINCE2 Controls
- Project Startup
- Quality Expectations and Acceptance Criteria
- Quality Management Strategy
- Quality review technique
- Report Highlights
- Reporting PRINCE2 Stage End
- Select the project approach and assemble the Project Brief
- Set up the PRINCE2 project controls
- Simple Study Aid
- Tailoring PRINCE2 Themes
- Take corrective action
- The Closing a Project Process
- The Controlling a Stage Process
- The Core Seven
- The Only PRINCE2 Sample Practitioner Exam Paper On The Internet!
- The PRINCE2 Business Case
- The PRINCE2 Change Theme
- The PRINCE2 Initiating a project process
- The PRINCE2 Process Sequence
- The PRINCE2 Processes
- The PRINCE2 Quality Review Technique
- The PRINCE2 Risk Management procedure
- The PRINCE2 Themes
- The Prince2 Process Sequence
- The risk management procedure
- prepare for planned or premature closure
- The PRINCE2 Article Library
- 38 Speedy Power Keys For Your PRINCE2 Project Health Check.
- Carrying out a PRINCE2 Quality Check
- The Product Description
- The plans theme and product based planning
- Creating a PRINCE2 Product Description
- PRINCE2 - Keeping Your Project On track - Part 2
- PRINCE2 Article Database
- PRINCE2 – Keeping Your Project On Track – PART 1
- The PRINCE2 Risk Theme – Uncertainty Mastered!
- The PRINCE2 Work Package
- The Secrets Of tailoring PRINCE2
- The Use and Content of the Issue Register and Issue Report
- PRINCE2 Foundation and Practitioner Exam Tips
- Agile verses PRINCE2 - a new species in evolution
- PART TWO of my Configuration Management In PRINCE2 Video
- PRINCE2 Quality
- Real-World PRINCE2 Planning
- Reviewing the progress on a PRINCE2 project
- Risk management
- Things You Might Not Know About PRINCE2
- The PRINCE2 Project Board and Governance
Configuration Management in PRINCE2
Configuration Management in PRINCE2
The PRINCE Manual does not make it very clear how and when Configuration Management is used. In particular, the manual does not list in one place, the many activities and how CM is used and applied. The Configuration Management is covered in the Change Theme, and is a good introduction to the main aspects that need to be considered.
Configuration Management Is Business-Critical. If you think it's just "admin" - then stop reading now...So this short article is intended to give you a flavour of the dynamics of CM within a PRINCE2 project. As always, don’t forget to scale the following information, including how formally each step is done.
The Configuration Management Strategy
The Configuration Management Strategy is created in the Initiating a Project process. The Project Manager liaises with the Configuration Librarian to discuss how the project will use and apply the CM system. The Configuration Management Strategy is drawn up. Don’t forget, it is a strategy - it is describing how to use and apply CM for this project.
Let's now deal with key points within a project where configuration Management will be used. Oh yes, and don't forget that itr is normally supplied by Project Support.
Authorise A Work Package. Update the Configuration Item Record to “under development” – the Configuration Librarian will do this. Ensure that the Work Package contains information regarding:
- How version control will work for the developer
- How to obtain copies of products or product descriptions
- How submission of the product to the Configuration Librarian will occur
- How the passing of product status information back to the Configuration Librarian will occur.
Assessing Progress. Capturing “actuals” and updating the status of products (CIR). The Configuration Librarian can provide a Product Status Account (PSA) if needed. As the name suggests, this is a report of the status of products in the record system, so that these can be checked against the real world.
If correct, then this confirms the real status.
Capturing and examining Project Issues and Risks. Project Support/Configuration Librarian could receive/document all Issues as well as maintain the Issue Log.
Reviewing Stage Status. Requesting a Product Status Account. This is normally done at the end of a stage, but may be requested at any time. The project manager and Configuration Management (usually provided by Project Support), to check CIR to ensure all products have status = completed as anticipated
Take Corrective Action. This is the project manager taking any actions needed - providing the Project/Stage is forecast to be within Tolerance. As a result of this, there may be changes to work already under way, or future planned work.
Remember, the Project Manager can't make any changes to "baselined" products, and that includes their Product Descriptions, without the agreement of the Project Board. The Configuration Librarian to make any products or their copies available, add new copies given out to the CIR, and update CIR for any status changes.
Escalating Project Issues. The Project Manager is now forecasting that Tolerance is to be exceeded. This may be as a result of an Issue or advice of a new risk. The Configuration Librarian will update CIR status and add links for any related Issue.
Receiving Completed Work Package. This is the specialist team or team manager needing to agree that a particular Work Package will be started. Configuration Librarian to update the CIR to a status of ‘completed’.
This means that all the products of a Work Package have passed their quality check and have been approved. Product is now baselined if not already done in Assessing Progress.
Execute a Work Package. Specialist Team to advise Configuration Librarian to update CIR status of each product (this may have been done via Checkpoint Reports given to the project manager). As each product is approved, and provided it's pysical state allows, it may be returned to ther Configuration Librarian at this time.
Alternatively, the actual product, if it's physical state allows, may not be returned until the Work Package is returned and confirmed as complete - coming up next...
Delivering a Work Package (back to the PM). Configuration Librarian to handle the return of completed products (if appropriate), and to assist Project Assurance in confirming customer/user acceptance of products.
Reporting the Stage End. Configuration Librarian with assistance of Project Assurance to confirm the CIR is same as actual status of products by carrying out a Configuration Audit. Also check that version numbers are correct/updated.
Producing an Exception Plan. Configuration Librarian will provide a Product Status Account of products to be replaced/incomplete. New CIR’s are created if needed. Remember, all future products Product Descriptions are at "draft" status until the Project Board approve the Plan containing them.
Closing a Project. CIR checked for completeness, and used as an input to Product Status Account – confirmation from customers configuration management records that all products are approved. Refer to the Configuration Management Strategy for how the products are to be handed over to those with support/operational responsibilities.
This is likely to be an item in Follow-on Action Recommendations. Carry out a Configuration Audit to check that all products are approved and complies with their CIR’s.
Define and Analyse the Products. This occurs in the product-based planning technique. The Configuration Item Record is created with reference to the Configuration Management Strategy.
In PRINCE2, all Plans are documents, and the Product based planning technique (contained within the Plans Theme), is used to create those documents, and it is here that CM will need to be involved in the intial (or updating/refinedment) of each CIR.
Configuration Management SUMMARY.
Please don't forget these Key Facts:
- CM is a Tool and a Service
- Cm is MANDATORY
- CM will be used for ALL Specialist Products
- CM will be used for all Management Products - apart from the Registers and Logs.
Within PRINCE2, CM is basically "Version Control" - but consider how CM will need to do the following "in practice":
1. CM is a service - so it MUST be a permanent part of your organisation - before and after the project even exists - forever in fact - even beyong the product life - (consider, just because you run an old system...or a car....imagine how you'd feel to be told "we don't support that anymore"!
2. Manage, track and keep control of all the products
3. Have a library with structure so that each product's status can be recorded
4. Control access to each product, and how it will be stored in a secure way (when appropriate).
5. A suitable system for logging, tracking, and filling of product issues (which, of course, includes changes).
Finally, on a practical basis, how all the above will ensure that products are identified, booked in and booked out, and how copies will be dealt with (mostly with documents). Scale the whole thing. If a locked filing cabinet in the corner of an office is appropriate - with appropriate human interface - then fine.



