- Pass The PRINCE2 Exam First Time
- PRINCE2 In Bite-Sized Chunks.
- Key Foundation and Practitioner Learning Points - PRINCE2
- Change Management
- Managing and Controlling a PRINCE2 Delivery Stage
- PRINCE2 Project Closure
- PRINCE2 Starting Up A Project Process
- Using PRINCE2 Initiating A Project Process
- PRINCE2 Authorizing Initiation
- The PRINCE2 Controlling a Stage Process
- Appoint The Executive and Project Manager
- Authorising a PRINCE2 Project
- Authorize a Stage or Exception Plan
- Authorize a Work Package
- Capture and Examine Issues and Risks
- Change Control
- Change control procedures
- Configuration Management
- Configuration Management and Change Control
- Controlling a stage
- Create the PRINCE2 Communication Management Strategy
- Creating a PRINCE2 Plan
- Design and appoint the Project Management Team
- Execute a PRINCE2 Work Package
- Give Ad-hoc direction in a PRINCE2 project
- Hand over products and evaluate a PRINCE2 project
- Managing A Stage Boundary
- Managing Product Delivery process
- PRINCE2 - Authorise Project Closure
- PRINCE2 - Directing a Project PRocess
- PRINCE2 Configuration Management and Change Control
- PRINCE2 Controls and Tolerance
- PRINCE2 Estimating Techniques
- PRINCE2 Management Stages
- PRINCE2 Plans
- PRINCE2 Principles
- PRINCE2 Product-based Planning video
- PRINCE2 Product-based planning technique
- PRINCE2 Progress reporting
- PRINCE2 Quality Theme
- Plan The Next Stage or Exception Plan
- Plan the Initiation Stage in PRINCE2
- Prepare the PRINCE2 Quality Management Strategy
- Prepare the Risk Management Strategy
- Prepare the outline Business Case
- Product Based Planning
- Project Board and Project Manager PRINCE2 Controls
- Project Startup
- Quality Expectations and Acceptance Criteria
- Quality Management Strategy
- Quality review technique
- Report Highlights
- Reporting PRINCE2 Stage End
- Select the project approach and assemble the Project Brief
- Set up the PRINCE2 project controls
- Simple Study Aid
- Tailoring PRINCE2 Themes
- Take corrective action
- The Closing a Project Process
- The Controlling a Stage Process
- The Core Seven
- The Only PRINCE2 Sample Practitioner Exam Paper On The Internet!
- The PRINCE2 Business Case
- The PRINCE2 Change Theme
- The PRINCE2 Initiating a project process
- The PRINCE2 Process Sequence
- The PRINCE2 Processes
- The PRINCE2 Quality Review Technique
- The PRINCE2 Risk Management procedure
- The PRINCE2 Themes
- The Prince2 Process Sequence
- The risk management procedure
- prepare for planned or premature closure
- The PRINCE2 Article Library
- 38 Speedy Power Keys For Your PRINCE2 Project Health Check.
- Carrying out a PRINCE2 Quality Check
- The Product Description
- The plans theme and product based planning
- Creating a PRINCE2 Product Description
- PRINCE2 - Keeping Your Project On track - Part 2
- PRINCE2 Article Database
- PRINCE2 – Keeping Your Project On Track – PART 1
- The PRINCE2 Risk Theme – Uncertainty Mastered!
- The PRINCE2 Work Package
- The Secrets Of tailoring PRINCE2
- The Use and Content of the Issue Register and Issue Report
- PRINCE2 Foundation and Practitioner Exam Tips
- Agile verses PRINCE2 - a new species in evolution
- PART TWO of my Configuration Management In PRINCE2 Video
- PRINCE2 Quality
- Real-World PRINCE2 Planning
- Reviewing the progress on a PRINCE2 project
- Risk management
- Things You Might Not Know About PRINCE2
- The PRINCE2 Project Board and Governance
Authorize a Stage or Exception Plan
Authorise a Stage or Exception plan.
The project board use this activity for one of two situations, either to approve the next Stage Plan as the current stage reaches completion, or to approve an Exception Plan if at some point during the current stage, the project manager had forecast that tolerance will be exceeded. Of course, the project board may choose to prematurely close the project.
In making this decision, the project board will want to look back and ensure the current stage has proceeded satisfactorily, look up, and ensure that the Project Plan and Business Case remain viable, and look forward, by approving the next Stage Plan. The important principle here is that the next stage is not started until the project board have authorised it.Remember, that the project board only have the authority to set the stage level tolerances, and if at any point project tolerances are forecast to be exceeded, then the project board must escalate this to corporate all programme management for their decision on what to do next. The project board may appoint project assurance to carry out some of the reviewing of draft documentation prior to them Authorising a Stage or Exception Plan.
Authorise a stage or exception plan activity is therefore either used for an end stage assessment or for an exception assessment. The project board must review and approve the following:
Check that any deviations and current forecasts for the project are satisfactory, and if needed review the Lessons Report. The project board must check that the aggregated risks are still acceptable and that risk responses are realistic and incorporated within the appropriate plan.
Some projects will hand over products to the customer or users during the project rather than just at the end of the project. If so, then the project board must satisfy themselves that product hand over occurred in line with the Configuration Management Strategy, and that user, operational, and maintenance acceptance has occurred. There may also be some follow-on action recommendation, and the project board will want to ensure that the appropriate groups have accepted such responsibilities.
Whether the project board are being asked to confirm a Stage or Exception Plan, then product based planning will have occurred and they should review and approve any new or modified Product Descriptions. Also the four Strategy documents, Project Plan, Business Case, and Benefits Review Plan will have been updated as appropriate, and the project board must review and approve these.
The project board have the following choices in making a decision for the remainder of the project:
Approve the plans, ensure resources are available, set tolerances for the next stage, advise the project manager how often they want to receive the Highlight Report for the next stage, and authorise the project manager to proceed.
They may reject some of the documentation and ask the project manager to make alterations or corrections, and come back to them for an approval.
They may instruct the project manager to initiate premature closure of the project.
Finally, the project board must communicate the status of the project to corporate or programme management is and any other interested parties as laid out within the Communication Management Strategy.
For more information on PRINCE2 - GO HERE



