The Use of Configuration Management in PRINCE2


The PRINCE Manual does not make it very clear how and when Configuration Management is used. In particular, the manual does not list in one place, the many sub-processes and how CM is used and applied.
The Configuration Management Component - is a good introduction to the main aspects that need to be considered.

Configuration Management Is Business-Critical. If you think it's just "admin" - then stop reading now...So this short article is intended to give you a flavour of the dynamics of CM within a PRINCE2 project. As always, don’t forget to scale the following information, including how formally each step is done.


IP1 – Planning Quality.

The Configuration Management Plan is created. The Project Manager liaises with the Configuration Librarian to discuss how the project will use and apply the CM system. The Configuration Management Plan is drawn up. Don’t forget, just like the Project Quality Plan (which contains the CMP), it is really a strategy (How to use and apply CM for this project).

IP5. Setting Up Project Files

Takes information from the Project Plan, and adds project filing structure to the Configuration Management Plan. CM system may already have these facilities. Responsibilities for CM may cause the filing to be updated.

CS1. Authorising Work Package

Update the Configuration Item Record to “under development” – the Configuration Librarian will do this. Ensure that the Work Package contains information regarding:

  • How version control will work for the developer
  • How to obtain copies of products or product descriptions
  • How submission of the product to the Configuration Librarian will occur
  • How the passing of product status information back to the Configuration Librarian will occur.

CS2. Assessing Progress.

Capturing “actuals” and updating the status of products (CIR). The Configuration Librarian can provide a Product Status Account (PSA) if needed. As the name suggests, this is a report of the status of products in the record system, so that these can be checked against the real world.

If correct, then this confirms the real status.

CS3. Capturing Project Issues and
CS4. Examining Project Issues.

Configuration Librarian could receive/document all Issues as well as maintain the Issue Log.

CS5. Reviewing Stage Status.

PM/Configuration Librarian to check CIR to ensure all products have status = completed as anticipated

CS7. Taking Corrective Action.

This is the proejct manager taking any actions needed - providing the Project/Stage is forecast to be within Tolerance. As a result of this, there may be changes to work already under way, or future planned work.

Remember, the Project Manager can't make any changes to "baselined" products, and that includes their Product Descriptions, without the agreement of the Project Board. The Configuration Librarian to make any products or their copies available, add new copies given out to the CIR, and update CIR for any status changes.

CS8. Escalating Project Issues.

The Project Manager is now forecasting that Tolerance is to be exceeded. This may be as a result of an Issue or advice of a new risk. The Configuration Librarian will update CIR status and add links for any related Issue.

CS9. Receiving Completed Work Package.

Configuration Librarian to update the CIR to a status of ‘completed’. This means that all the products of a Work Package have passed their quality check and have been approved. Product is now baselined if not already done in Assessing Progress (CS2).

MP2. Executing a Work Package.

Specialist Team to advise Configuration Librarian to update CIR status of each product (this may have been done via Checkpoints and CS2 via the PM). As each product is approved, and provided it's pysical state allows, it may be returned to ther Configuration Librarian at this time.

Alternatively, the actual product, if it's physical state allows, may not be returned until MP3 - coming up next...

MP3. Delivering a Work Package.

Configuration Librarian to handle the return of completed products (if appropriate), and to assist Project Assurance in confirming customer/user acceptance of products.

SB5. Reporting Stage End.

Configuration Librarian with assistance of Project Assurance to confirm the CIR is same as actual status of products by carrying out a Configuration Audit. Also check that version numbers are correct/updated.

SB6. Producing an Exception Plan.

Configuration Librarian will provide a Product Status Account of products to be replaced/incomplete. New CIR’s are created if needed. Remember, all future products Product Descriptions are at "draft" status until the Project Board approve the Plan containing them.

CP1. Decommissioning a Project.

CIR checked for completeness, and used as an input to Product Status Account – confirmation from customers configuration management records that all products are approved. Refer to the Configuration Management Plan for how the products are to be handed over to those with support/operational responsibilities.

This is likely to be an item in Follow-on Action Recommendations. Carry out a Configuration Audit to check that all products are approved and complies with their CIR’s.

PL2. Defining and Analysing Products.

The Configuration Item Record is created with reference to the Configuration Management Plan.

In PRINCE2, all Plans are documents, and the Planning Process is used to create those documents. But, the Product-Based Planning Techniques is used in PL2, and it is here that CM will need to be involved in the intial (or updating/refinedment) of each CIR.

Configuration Management SUMMARY.

Please don't forget these Key Facts:

  • CM is a Tool and a Service
  • Cm is MANDATORY
  • CM will be used for ALL Specialist Products
  • CM will be used for all Management Products - apart from the Logs.
  • Within PRINCE2, CM is basically "Version Control" - but consider how CM will need to do the following "in practice":

1. CM is a service - so it MUST be a permanent part of your organisation - before and after the
  project even exists - forever in fact - even beyong the product life - (consider, just because
  you run an old system...or a car....imagine how you'd feel to be told "we don't support that
  anymore"!

2. Manage, track and keep control of all the products

3. Have a library with structure so that each product's status can be recorded

4. Control access to each product, and how it will be stored in a secure way (when appropriate).

5. A suitable system for logging, tracking, and filling of product issues (which, of course, includes changes).

Finally, on a practical basis, how all the above will ensure that products are identified, booked in and booked out, and how copies will be dealt with (mostly with documents). Scale the whole thing. If a locked filing cabinet in the corner of an office is appropriate - with appropriate human interface - then fine.

 

I've got a copy here with your name on it - don't let the person next down my list grab yours!

CLICK HERE

...coaching students to absorb and understand Prince2
quickly and easily by guiding and steering them to Pass potential
without the need of a classroom...

CLICK HERE

prince2:2009

prince2

 

 

 

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Hi Dave,

Many thanks. I have downloaded your PRINCE2009 zip files. Had a quick look at the pdfs and started the first video.

Wow, … it is so nicely done. I’ll be recommending them to anyone I know who might need it.

Lavinia A.
Home Office
UK

 
 
 
 
 
 
 
 
 
 
 
 

Hello Dave,

Just thought I should pass on some good news to you! I've just received the exam results for my PRINCE2 Practitioner and I passed with 60%!

I went through your PRINCE2 Primer videos three times and dipped into the official manual once afterwards.

The exam was pretty tough and I don't think I would have passed if it had not been for your training skills and materials.


Many thanks for your help. I must confess I actually enjoyed studying your PRINCE2 Primer as it enlightened my understanding of PRINCE2!

Best wishes

Abdul Khan

 
 
 
 
 
 
 
 
 
 
 
 

Hi Dave,

Just thought I would drop you a quick line from a (remarkably) sunny Leeds to say another thank you for the recent Prince 2 course you delivered, I doubt its much of a match for Spain but any sun is welcome!

Our results have come through now and I scored 80% on the Practitioner Exam and I can wholeheartedly say this is down to the way you managed to turn that initially inaccessible-looking Prince2 Manual into manageable and practical advice for the exam.

Many thanks again, as I stated on my evaluation form, the course you delivered was by far the best I have been on and hopefully it has set me up nicely to develop as a project manager.

Best wishes,

Keir Shillaker
Bradford Teaching Hospitals
NHS Foundation Trust
 
 
 
 
 
 
 
 
 
 
 
 

Dave,


I am tingling all over with the advice that I have just passed the Prince2 Practitioner Exam (24.April.09)

Your Primer course is without doubt the main reason for my success.

Thanks to your teaching I obtained a 78% pass. I am Elated.

I wish you continued success and would encourage any prospective students to purchase your primer course.

May thanks .
Best regards

Raymond
(Full name and address on file)

 
 
 
 
 
 
 
 
 
 
 
 

Dave,

Your Primer is not just "promising" -- it is a highly professional work reflecting a quality level very-very close to excellence.

I am sure that I am just one more individual joining the long queue of your PRINCE2™ Primer FanClub !

My sincere congratulations and many thanks for providing the PRINCE2™ management Community with such a quality product at such a friendly price!

Colonel Nikolaos D
Chief of Integrated Logistics Program,
ASQ, CMQ/QE

 
 
 
 
 
 
 
 
 
 
 
 

From: John Robertson
To:
dave@davelitten.com
Sent: Thursday, November 20, 2008 2:01:15 PM
Subject: PRINCE2 Practitioner

Afternoon Dave, Hope you are well and the business is still going strong. I took the PRINCE2 Practitioner Exam on the 31st October 2008.

I found out today that I passed with 270 marks out of a total of 360 marks (a clear 75%!)I had no classroom interaction at all, just pure reading and the experience already gained from using your PRINCE2 PRIMER.

The Practitioner course I went on was to give pointers (which I had already from your Primer) and nothing extra that was crucial to pass the exam.
So I felt a little slighted that I paid £700 for a 1.5 day course that consisted of 1 day of revision and half a day Practitioner Exam!

Your PRINCE2™ Primer was spot on...........Again thank you for all your help...it was very much appreciated
......excellent product!

Kindest regards

John Robertson

 
 
 
 
 
 
 
 
 
 
 
 

Hi Dave,

Just a little note to say a big thank you for your PRINCE2™ PRIMER.

Thanks to just the PRINCE2™ Manual together with your help, I've PASSED both the PRINCE2™ 
Foundation and the Prince2 Practitioners Exams !!

Cheers Dave,

Noj

Manoj Sanghera
Thu 18 December 2008 09:15

 
 
 
 
 
 
 
 
 
 
 
 

PRINCE2™ COURSE 'ROCKS'
IN THE STATES!!!

"Dave Rocks! The best trainer we've ever had. His humour kept me laughing. Wish all trainers were like him!"

Course attendee
IT Training Manager
Sun Microsystems
San Francisco

 
 
 
 
 
 
 
 
 
 
 
 

7 March 2009

Dear Dave,

I would like to thank you. I passed the PRINCE2™
Practitioner Exam last week.

Due to the fact I was very busy at the office I did not have anytime to read the Prince2 Manual -- instead...

I just watched your videos once.

In combination with the training I had and my own experience it was enough for me to Pass.

Thank you again.

Kind regards,

Faizal Jung Siddiqui
IT Project Manager
Netherlands 

 
 
 
 
 
 
 
 
 
 
 
 

MORE TESTIMONIALS

Read the feedback my
PRINCE2 PRIMER
has received...
 

"Dave was fantastic in teaching his subject;
he really came across well and helped me understand"

----------

"Very engaging and supportive - his knowledge was amazing!

 ----------

"Would rate Dave as one of the best instructors
I've had the pleasure
to learn from"

----------

"Very engaging - contagiously passionate!"

-----------

"Knew his stuff - and explained it very well"

----------
"Thank Goodness I had Dave as my teacher..."

----------

"Well drilled, covered all aspects more than once from different angles"

----------

"...by far - the best instructor and teacher I have ever had!..."
----------


"Dave was Great!"

----------
"Extensive knowledge of skills and techniques - inspired confidence
- Thanks Dave!"

----------

"First-Class Instructor - unable to fault"

----------

"Made the material approachable and understandable
no matter what your
current knowledge-level"

----------

"Excellent instructor, teaching skills above expectations,
kept me focused and provided information
on key skills.

----------
"Provided good examples
to explain concepts,
taught the subject
rather than just reading from PowerPoint slides"

----------

"Very good. Strongly recommended"

-----------
"Really good. Kept me motivated and engaged throughout"

----------
"Outstanding"

----------

"Great teaching skills - confident and engaging"

----------
"Excellent Instructor
all-round"

----------

"Very knowledgeable and delivered topics really well"